The Freight Lift Sizes the Trampoline Module, Not the Plan
A trampoline court is drawn twice. The first drawing is approved in a meeting room, and it is the one everybody remembers. The second has to pass through a 1.9 m door at the back of a shopping centre, and the second drawing is the one that gets built.
Developers check ceiling height first, and that is correct. It decides whether a slide tower, a high platform or a ninja rig exists at all, which is why we treat it as the first number to check. Floor load comes second, because the slab decides whether the building can carry a jumping crowd.
Access comes third, and it is the constraint that never makes it onto the schedule. It rarely kills a project outright. It raises the price, shortens the court and moves the opening date, and it does all three after the equipment has been paid for.
This article is about that third constraint: how the route sets the module, how to survey it in an afternoon, and what a field modification really costs. We write from the supplier side, where the argument usually arrives as a photograph of a door with a tape measure across it.
One boundary before the detail. No trampoline standard covers this. ASTM F2970-22 covers the design, manufacture, installation, operation, maintenance, inspection and major modification of courts. ISO 23659:2022 covers the design, construction, inspection and maintenance of parks, and it explicitly excludes general building regulations and fire regulations. The lift, the door and the slab belong to the building, and the building has its own rules.
1. Why the Route Outranks the Room
The four building constraints are not equal, because they fail at different moments. A ceiling that is too low fails at the first site visit. A slab that is too thin fails at the structural survey. A route that is too tight fails at 07:40 on the delivery morning, when the truck is on the dock, the driver is on the clock and the equipment is already paid for.
That timing difference is the whole argument. Constraints that fail early cost a survey fee. Constraints that fail late cost a crane, a night shift and a modified frame.
| Constraint | What it actually kills | When it is normally discovered | Cost to fix after design freeze |
|---|---|---|---|
| Ceiling height | The attraction, not the lease: no tower, no high platform, no full-height rig | First site visit | Redesign of the zone plan, with the rent unchanged |
| Floor load | The location, or the court layout on that slab | Structural survey, before lease signature if you are careful | Structural strengthening, or a smaller court in the same room |
| Delivery route | The module size, and with it the assembly hours and the court geometry | On the delivery day, or at the first packing list | Crane, night shift, factory re-split, site welding, coating repair |
| Egress | The usable layout, because exit width sets occupancy | Fire strategy review | A re-plan of the whole floor plate, sometimes a smaller box |
The asymmetry is easy to remember. The ceiling and the slab decide what the building can hold. The route and the egress decide what you can put in it and still open on the date you promised.
The one-hour test: a route survey takes about an hour with a tape, a torch and a phone camera. A factory re-split takes two to three weeks and a new packing list. A site modification takes the same fortnight, and adds a coating repair and a documentation problem that outlives the project.
2. What Actually Arrives on the Truck
Buyers picture a court arriving as a court. It arrives as a stack of long steel, a roll of bed fabric, boxes of springs, panels of padding and a bundle of netting. The steel sets the constraint, because steel does not fold, compress or turn a corner without becoming a different component.
The other parts forgive more, but only up to a point. Padding is rigid foam wrapped in PVC, so it is bulky and light, and a panel slightly too long can sometimes be trimmed without touching the frame. Bed fabric rolls, springs arrive boxed, netting is soft. None of that helps if the frame bay is wider than the lift door.
| Component | Ships as | What governs its packed size | Can it be reduced on site |
|---|---|---|---|
| Frame bays and legs | Welded or bolted steel sections, bundled | The bay’s outside dimension, plus bundling and stillage | No, not without a documented modification |
| Jump beds | Rolled fabric with edge webbing | Roll diameter, not length | Yes, within the manufacturer’s fitting allowance |
| Springs | Cartons, dense | Weight per carton, not size | Not applicable |
| Padding panels | Rigid foam cores in PVC sleeves | Panel length, which follows the bay | Sometimes, with a new sleeve |
| Netting and poles | Bags and tube bundles | Pole length, often the longest item shipped | Poles can be jointed if designed for it |
| Airbag or foam | Folded bag, or compressed foam blocks | Bag mass and foam volume | Foam can be cut; a bag cannot |
2.1 The container door is the first door the module has to pass
ISO 668:2020 classifies series 1 freight containers by external dimension, sets the associated ratings, and specifies minimum internal and door opening dimensions where those apply. A 40 ft high-cube has roughly 2.35 m of internal width and a door opening a little narrower than that, so a module wider than the opening cannot be loaded in the first place.
This produces a shortcut. Every module you receive has already passed the container door, so the packed width is a ceiling on the problem. When a court does not fit, the binding opening is almost always the freight lift or the tenant door, not the shipping container.
The arithmetic that matters is a minimum, not an average:
max_module_width = min(container door, lift door, tenant door, stair clear width,
narrowest point on the internal route) - 2 x handling clearance
payload check = heaviest single item x number of trips, against lift rated load
and against the slab rating where the trolley stops
Handling clearance is not a fixed number, because it depends on the trolley, the turn and the crew. Treat anything within a hand’s width of the opening as a no. A frame that fits with 20 mm to spare will fit once, on a dry day, with the leaf taken off and four people lifting evenly. It will not fit again when the padding is already on and the crew is tired.
2.2 Ask for packed dimensions, not total weight
If your packing list gives one total weight, it is decoration. What the site needs is a list of the five largest items with length, width, height and mass for each, plus the heaviest single item on its own. Ask for that before the deposit, not after the production slot is booked.
Two questions do most of the work:
- What is the largest single thing that will arrive, and what does it weigh? If the answer is a frame bay at 2.4 m, the survey has a target.
- Can that item be split at the factory, and what changes if it is? A bolted splice designed in the works is a detail. A splice invented on site is a modification.
3. The Five Openings, and How to Measure Them
A route survey is not a walk-through with a phone. It is five measurements and one drawing. Do it before the lease is signed, or make the lease conditional on it, because after signature the only remaining lever is money.
3.1 The dock or ramp
Measure the clear width between the dock leveller and the wall, the height of the roller shutter when it is fully up, and the gradient of any ramp. A loaded pallet truck on a slope is a manual handling problem before it is a delivery problem, and a shutter box that hangs into the opening will stop a bundle the door width already allowed.
3.2 The freight lift
This is where most projects lose their module size. Four numbers matter and they are rarely on the same drawing: door clear width, door clear height, car floor dimensions and rated load. Add the lobby depth, because a long bundle needs room to turn before it enters, and the sill height, because a step of a few centimetres under a trolley wheel is a stop rather than a bump.
The figure on the plate is not the same as the load the building will accept. Ask the building manager for the lift specification, the last inspection date and any restriction on goods traffic.
3.3 The tenant door
Nominal door sizes describe the frame, not the opening. Leaf, hinges, closer arm and fire door hardware all sit inside the clear width, and a fire door cannot be propped. Measure from the door stop to the face of the closed leaf, with the door at 90 degrees.
3.4 The stair, the lobby and the corner
Where the lift is too small, the route becomes the stair or the escalator void, and both are worse. Measure the turning rectangle rather than the width: a wide corridor with a 90 degree turn into a narrow doorway will not pass a long bundle.
3.5 The route inside the room
Columns, downstands, sprinkler heads, cable trays, ductwork and any change in floor level all sit between the door and the court. The lowest obstruction sets the vertical clearance for the whole route, and it is usually a sprinkler head or a beam that nobody photographed.
| Opening | What to measure | The number people get wrong |
|---|---|---|
| Dock or ramp | Clear width, shutter height, ramp gradient, kerb height | Shutter height with the box, not with the slats |
| Freight lift | Door clear width and height, car floor, rated load, sill step | Lobby depth needed to turn the bundle |
| Tenant door | Clear width at the narrowest point, threshold, closer | Frame size quoted as clear width |
| Stair or lobby | Turning rectangle, headroom, handrail projection | Corridor width quoted instead of the turn |
| Internal route | Lowest obstruction, column spacing, floor level changes | Sprinkler heads and downstands |
Photograph every opening with the tape visible and the reading legible, and label each photo with its location. A supplier who receives eleven unlabelled photographs of doors will design to the smallest one, and the court will be smaller than it needed to be.
4. Point Loads, Thresholds and the Slab You Roll Across
A trolley carrying two tonnes does not spread that load across the floor. It puts it through four wheels, each of which is a point load on a slab that may be rated for retail shelving. Protective plates spread the load, and the plates need to be on the route before the first bundle arrives, not after the first crack appears.
This is a different question from the one a structural engineer answers for the finished court. Deflection under a jumping crowd and a point load from a trolley are separate checks, and a slab that passes the second can still fail the first. We covered the operating case in the article on floor load and slab capacity; the delivery case belongs with the same engineer.
Flatness is the second floor question, and it shows up months later. The frame is assembled on the slab, so local undulations become shims, and a frame that is level but not flat carries uneven bed tension from the first day. The fix is a levelling scope nobody budgeted.
Thresholds are the third: one a couple of centimetres high is invisible on a drawing and decisive under a wheel, so plan a plate or a ramp before the first trolley reaches it.
5. What a Field Cut Really Costs
Sooner or later someone says the sentence: we will cut it here and weld it on site. It is said in good faith, usually by a competent installer, and it is almost always the most expensive sentence in the project. Three ledgers change at once.
5.1 The coating ledger
ISO 1461:2022 specifies the properties and test methods for hot dip galvanized coatings applied by dipping fabricated iron and steel articles in a zinc melt. It also states that it does not apply to after-treatment or additional coating of hot dip galvanized articles. A zinc-rich patch painted onto a cut edge is therefore not an ISO 1461 coating. It is a second protective system, applied by hand, with a different service life, in a hall that runs warm, humid and chlorinated from the water play and the cleaning regime.
The cut edge and the weld are where corrosion starts, and where a coating survey looks first. A dipped frame is a single system; a cut and patched one is a system with a joint, and the joint is the weakest part.
5.2 The documentation ledger
In Europe, load-bearing steel components placed on the market are assessed under EN 1090-1, the harmonised standard that sits under Regulation (EU) No 305/2011. That assessment rests on factory production control, an execution class from EXC1 to EXC4, and a Declaration of Performance. The declaration describes a component made under that control, in that works, to that class.
Work done in a mall corridor sits outside that control. The article on site no longer matches the paper that travelled with it, and the party who signs for it is the party who did the work. Before anyone picks up a grinder, ask the fabricator what they will sign for the component after the change, and who carries the declaration then.
5.3 The structural ledger
A frame bay is a load path, not a rectangle of tube. Cutting a chord or a leg and re-welding it in the field changes the section at that node, the weld detail and the corrosion protection at the same point, and it does so without a welding procedure or a qualified welder on site. ASTM F2970-22 gives major modification its own section, alongside separate sections for the information plate and for certifications, which tells you how the practice treats a change of this kind: as a documented event with an owner, not as a site decision.
| Ledger | What changes | Who carries it | When it shows up |
|---|---|---|---|
| Coating | One dipped system becomes dipped steel plus a hand-applied patch | The operator, over the life of the frame | First inspection, or the first winter of condensation |
| Documentation | The declaration describes a component that no longer exists as described | Whoever signed for the modification | At handover, at insurance renewal, or at the first incident review |
| Structure | Load path, weld detail and section at one node | The operator, in practice | Under load, which is to say with children on the court |
| Schedule | Assembly hours, inspection, repainting, cure time | The operator, in rent and payroll | The week the opening slips |
There is a fourth ledger that never reaches an invoice. A court cut to fit a door is a court with a joint in it, and the joint sits inside the play area where a bed, a spring line and a padding run all have to accommodate it. The cost is not the welding. The cost is the decade of inspection and repair that follows.
6. What Shrinking a Module Costs Inside the Court
The tempting fix is to order narrower modules. It sounds like a drawing change and it behaves like a product change, because the module is the unit the whole court is built from: the bed, the spring count, the padding length, the net line and the leg spacing all follow it.
Narrower modules do let more bays fit across a fixed width. They also raise the ratio of edge to jumping surface, and the edge is where the frame, the padding and the net all live. The arithmetic is unforgiving:
beds per row = floor((available width - 2 x edge zone) / module width) waste per row = available width - beds x module width edge ratio = perimeter padding length / bed area assembly hours ~ f(number of bays, number of splices, number of springs)
A worked example makes the trade visible. Assume 24.0 m of clear width inside the hall, an edge zone of 0.6 m on each side, and a module of 2.44 m, which is the 8 ft bay many courts are built from.
| Option | Module | Beds per row | Width used | Waste per row | What changes |
|---|---|---|---|---|---|
| A: standard bay | 2.44 m | 9 | 21.96 m | 2.04 m | Nothing; the waste becomes corridor |
| B: narrower bay | 2.20 m | 10 | 22.00 m | 2.00 m | Smaller bed per bay, more legs, more springs per metre |
| C: factory split | 2.44 m, split to 1.22 m | 9 | 21.96 m | 2.04 m | More splices and assembly hours, same court |
Option B looks efficient and is usually wrong. Ten smaller beds are not ten standard beds: total bay width barely changes, the frame count rises, and the padding line grows with the perimeter. Option C keeps the product and moves the cost into the factory and the assembly shift, where it can be planned, priced and inspected.
There is a layout consequence too. If the court is redrawn late to fit a route, the strip that disappears was going to be circulation, spectator seating or the party room wall, and those are the parts that generate revenue. The egress calculation then has to be rerun, because exit width sets the occupant load, and a narrower court with the same doors may hold fewer people than the business plan assumed.
7. The Sequence That Keeps the Design Intact
The order of decisions matters more than the effort spent on each one. Six steps, in this sequence, keep the module and the court geometry from being decided by a door.
Step 1. Survey the route before the lease. One hour, one tape, five openings. If the landlord will not give access before signature, make the survey a condition of the lease. This is the only step where a bad answer still costs nothing.
Step 2. Send the survey to the manufacturer before design freeze. Photographs with tapes, plus the lift specification and the rated load. A designer who knows the lift door is narrow will draw a court that fits through it. A designer who finds out later will draw a court that gets cut.
Step 3. Get packed dimensions and masses in writing. Five largest items, the heaviest single item, and the container loading plan. Compare them against the survey, not against the drawing.
Step 4. Decide the split points at the factory. If something has to be smaller, it should be smaller before it is galvanized, bundled and loaded. A designed splice is a detail; an invented splice is a modification.
Step 5. Agree the hoisting plan and the delivery window with the landlord. Crane position, permits, trading hours, night works, floor protection and insurance. A crane that arrives without a permit is a crane that goes home.
Step 6. Sequence deliveries zone by zone. Frames and beds first, padding and netting last, so finished surfaces are not on the route while steel is still moving. Inspect on arrival, before assembly.
| Step | Decision | Who owns it | Cost of changing it later |
|---|---|---|---|
| 1 | Does the route accept a standard module | Owner, with the landlord | Everything downstream |
| 2 | Court geometry and zone plan | Designer and owner | Redraw, re-quote, re-permit |
| 3 | Packing list and container plan | Manufacturer | Re-split, new coating, new crates |
| 4 | Splice design and assembly method | Manufacturer and installer | Site welding, coating repair, documentation |
| 5 | Hoisting, permits, delivery window | Owner, landlord, contractor | Crane re-hire, night premium, lost trading day |
| 6 | Delivery sequence and inspection | Installer | Rework, damaged surfaces, warranty dispute |
8. Where the Invoice Lands
Access failures are cheap to prevent and expensive to solve. The invoice rarely arrives as one line; it arrives as five, spread across four suppliers and two months.
| Failure | Cost driver | How to size it before it happens |
|---|---|---|
| Module will not pass the lift | Crane hire, permits, night labour, lift out of service | Crane day rate x days + permit fees + night premium x hours |
| Module will not pass the tenant door | Frame removal, facade works, temporary weather protection | Glazing or panel removal quote + making good + security |
| Field cut and weld | Coating repair, re-inspection, documentation, shorter life | Transport both ways + re-dip, or the cost of a patch and its shorter life |
| Opening slips | Rent, payroll, debt service, utilities with no revenue | (Monthly fixed cost / 30) x days of delay |
| Court shortened | Lost capacity, redrawn layout, new egress check | Lost bed area x revenue per bed per year, from your own model |
The delay line is the one that compounds. In an earlier piece we costed a 100-day late opening at $321,400 in carry, which works out at about $3,214 a day, and most of that is rent and payroll while the doors stay shut. That figure rests on specific assumptions and is not a forecast, but the shape holds: every day of access problem is a day of fixed cost with no offsetting revenue. The full working is in the analysis of opening delays.
Freight is a separate and smaller line. Container loading, shipping and port charges behave predictably, which is why they belong in a budget; that arithmetic is in the container cost breakdown. Access is the unpredictable one, because it is a property of the building rather than of the shipment.
9. The Judgment Table
Five conditions cover most of the decisions we see. Read down the left column until one matches, then take the row.
| If this is true | Then do this | Do not do this |
|---|---|---|
| Every opening clears the standard module with room to spare | Order the standard bay, and spend the survey hour on something else | Redesign the court for a constraint that is not there |
| One opening is tight but the module can be split at the factory | Split it in the works, with a designed splice and a documented assembly sequence | Plan to cut on site and paint the joint |
| The lift is too small and the building has a facade or roof opening | Price a crane and a permit before ordering, and book a night window with the landlord | Assume the crew will manage with a stair and a rope |
| The module cannot pass and no opening can be made | Change the site, or change the product to a format that fits | Order narrow bays and hope the court still works commercially |
| The route is fine but the slab is not rated for the trolley | Plates, a defined route and a written method statement | Move the load and inspect the slab afterwards |
Two boundaries we would rather state than paper over. No public dataset records how often trampoline modules are cut to fit a building, so we can give the mechanism and the cost structure, not the frequency. And no trampoline standard sets a number here, because the number belongs to the building. Anyone who quotes a universal minimum door width is quoting a guess.
What is universal is the sequence. Measure the route, send it to the factory, get the packing list, split in the works, then book the crane you may not need. Do it in that order and the drawing you approve is the drawing that gets built.
If you already have a site, send the route survey with the lift specification and we will tell you which module fits before you sign anything. Our design-to-delivery process starts with that survey, not with a layout. Padding, spring and netting specifications for a split bay are on the trampoline park accessories pages, and the standards we design to are summarised under safety standards.
FAQ
What door width does a trampoline park installation need?
There is no standard number, because the requirement is set by the largest packed component rather than by the building type. Ask the manufacturer for the packed dimensions of the five largest items, take the widest, and add handling clearance. In practice the freight lift door, not the tenant door, is the opening that decides the module.
Can a trampoline court be installed on an upper floor of a shopping centre?
Yes, and many are, subject to two separate checks. The slab has to carry the operating load of a jumping crowd, and the route has to accept the packed module. The delivery case adds a third: the point load of a loaded trolley, which is a different calculation from the crowd load and belongs with the same structural engineer.
Do we need a crane to install a trampoline park?
Only when the lift and the doors cannot take the module, and then usually for a few hours rather than a full day. A crane plan needs a position the truck can reach, a permit from the local authority in most jurisdictions, a booked window with the landlord, and insurance that covers the lift over the building.
Can a frame bay be cut and re-welded on site?
It can be done, and it should not be. A field cut breaks the hot dip coating, which ISO 1461:2022 does not cover once the article has left the zinc melt, and it takes the component outside the factory production control behind its Declaration of Performance. ASTM F2970-22 treats major modification as a documented act with its own section, so the question is who signs for the change, not whether it can be welded.
How long does a trampoline park installation take?
The drivers are court area, the number of bays and splices, crew size, lift availability and delivery sequencing, which is why a fixed number from a supplier is worth checking against a schedule with crew counts. Ask for the assembly sequence zone by zone and for the hours assumed per bay, then compare that with the access window the landlord will actually give you.
Sources
- ASTM International, “F2970-22 Standard Practice for Design, Manufacture, Installation, Operation, Maintenance, Inspection and Major Modification of Trampoline Courts”, 2022. astm.org/f2970-22.html
- ISO, “ISO 1461:2022 Hot dip galvanized coatings on fabricated iron and steel articles — Specifications and test methods”, edition 4, August 2022. iso.org/standard/81435.html
- ISO, “ISO 23659:2022 Sports and recreational facilities — Trampoline parks — Safety requirements”, November 2022. iso.org/standard/76556.html
- CEN-CENELEC, “EN ISO 23659:2022 Sports and recreational facilities — Trampoline parks — Safety requirements”, date of availability 30 November 2022. standards.cencenelec.eu
- ISO, “ISO 668:2020 Series 1 freight containers — Classification, dimensions and ratings”, edition 7, January 2020. iso.org/standard/76912.html
- European Union, “Regulation (EU) No 305/2011 laying down harmonised conditions for the marketing of construction products”, Official Journal of the European Union. eur-lex.europa.eu/eli/reg/2011/305/oj